Missoula County Fairgrounds notice of noise impact

Monster Truck Nationals
Friday, June 14 & Saturday, June 15, 2019
7pm - 10pm
Arena (outdoors)


Willard School abatement and demolition timing


Contractors will be on site starting with ground floor window and roof abatement on the old building. Once the windows are abated, they will have plywood or another barrier covering the windows until demolition occurs.


The demolition of the old building is scheduled to start on Monday, June 17, 2019 at 7:00 a.m. There will be parts of 6th St and Ash St. that will be blocked off to vehicle traffic during the demolition on June 17th.  There will also be fencing to keep pedestrians out of the demolition area.
 
The site will remain active with crews through mid-August while demolition is completed and the new parking lot and landscaping are finalized. We will keep you posted if any old bricks from the building will be available for the community to reuse.
 
Everyone at MCPS and Sletten Companies would like to offer our appreciation for your patience while this construction project continues in your neighborhood. If you have any questions or concerns during the remaining construction and demolition process, please address them to:
 
Burley McWilliams
MCPS Operations and Maintenance Supervisor
728-2400 ext. 3032



     
     


     
     
     
     