Hello Missoula neighbors,
Throughout the Mullan area, crews will be present the week of May 22 - 26. Kiewit and contractors will not be present on Monday, May 29, Memorial Day.
REMINDERS:
The newly paved England Boulevard extension between Flynn Lane and George Elmer Drive is CLOSED. Though paving is complete, the final painting and shoulder must be completed. This roadway will open for Memorial Day weekend.
PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!
School is in session! Please be mindful of traffic, bicyclists and children in the area.
All roadwork is anticipated to be fully completed by early June. Thank you for your patience and understanding.
---
CONSTRUCTION UPDATE
MARY JANE BOULEVARD
Seeding for landscaping in the roundabout medians will take place this week. Trails will be paved at the end of May. There will be a brief closure on Mary Jane Boulevard between Mullan Road and Melrose Place from May 30 – June 2. Detour routes will be indicated with signs.
Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane to complete seeding and striping. Trails will be paved at the end of May.
ENGLAND BOULEVARD
The paving is complete on England Boulevard. This week, striping and seeding will occur. Beginning Friday, May 26 (Memorial Day weekend), England Boulevard between Flynn Lane and George Elmer Drive will be open to drivers.
GEORGE ELMER DRIVE
The bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road. Paving in this area is complete. Curb and Median work will start this week, and continue into next. Luminaires installation continues this week. Landscaping, drainage improvements and curb will finish up work in this area.
FLYNN LANE
Work is completed at the Flynn Lane and Mullan Road intersection. Drivers may notice crews finalizing shoulder dirt work.
OVERALL PROJECT
Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.
Crews anticipate completing this roadwork by the first week of June, weather and material dependent.
The Montana Department of Transportation is conducting pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023, and will continue for approximately 10 weeks.
Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.
Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com.
Respectfully,
Becca MacLean, on behalf of the Mullan BUILD project team
--