Public Works & Mobility Department logo

Milling & Paving Work on Beckwith St. on May 25 & 30


This project includes curb-to-curb milling followed by paving on Beckwith St. from Brooks to Woodford. On Beckwith St. from Stephens to S. 6th, work will involve intermittent milling and paving. 

Milling is planned for Thurs., May 25, with paving scheduled for Tues., May 30, weather permitting. 

  • Beckwith St. from Brooks to Woodford will be closed only during work hours of 7 a.m. to 5 p.m. with signed detours. 
  • Work on Beckwith from Stephens to S. 6th will not require street closure, but flaggers will be present during work hours. 
  • Both street sections will be fully open outside of work hours.

Please drive slowly and cautiously through the construction area and neighborhood detours. If possible, please plan an alternate route on these construction days. 

A project area map, more information, and project updates, if needed, can be found on the City website at www.ci.missoula.mt.us/2681/Street-Maintenance-Projects.

If you have questions, please contact Brian Hensel, Public Works & Mobility Deputy Director of Streets, at 406-240-2742 or HenselB@ci.missoula.mt.us.

Thank you for your patience while we work to improve our city streets!