Good afternoon,

Roadwork continues on the Mullan BUILD project. Please remember to SLOW DOWN and be mindful of other cars, signage, crews and equipment when entering a work zone. 
 
The week of July 25 through August 1, drivers will notice utility work continuing on Mullan Road for the Mary Jane Boulevard roundabout in this location. A detour remains here. Soon, gravel placement will take place in preparation for paving.
 
Crews are also present at the north end of Mary Jane Boulevard for the connection through to Broadway. Paving will take place this week and Flynn Lane will be limited to one lane during paving operations. Crew members will be present to direct traffic.
 
Lastly, roadwork is taking place on the south and north end of George Elmer Drive. The north end of George Elmer Drive between Mullan Road and Bell Tower Road is closed through the end of the summer. Traffic will be detoured, and drivers should expect delays. 
 
Please prepare for 5-10 minutes of delays when traveling through any of the above work zones. Thank you for your patience and understanding. Our team’s number one priority is safety.
 
Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.
 
Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com. 
 
Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).
 
Take care,
Becca MacLean, on behalf of the BUILD Project Team 
--
Becca MacLean (she/her/hers)
Account Executive
Big Sky Public Relations
(406)-499-6921
becca@bigskypublicrelations.com
www.bigskypublicrelations.com 
 

Additional Links:

Neighborhood Councils, engagemissoula.com  City Council, City Calendar; City Meetings,  Planning Projects and Updates, Private Development Projects,  Public Infrastructure Projects, Board and Commission Vacancies, Missoula Redevelopment Agency Current Agenda, Citywide Events Calendar

Unsubscribe





Share on Facebook
Share on Twitter
Share via Email

Copyright © 2021 City of Missoula. All Rights Reserved.
435 Ryman Street Missoula, MT 59802

Powered by
CivicSend - A product of CivicPlus